Following gauges are provided in loco
1. Brake Cylinder Pressure Gauge
It is provided on both control stands. Brake cylinder pressure gauge shows 3.0 kg/cm² pressure on loco brake application.
2. Brake Pipe Pressure Gauge
It is located on both control stands. BP pressure gauge shows 5.0 kg/cm² on A9 release condition.
3. MR and FP Pressure Gauge
It is a duplex gauge and provided on both control stand. Left side needle shows MR pressure and right side shows FP pressure. MR pressure gauge shows 8-10 kg/cm² and FP pressure gauge shows 6.0 kg/cm².
3. Vacuum Gauge
It is provided on both control stands in dual brake loco. It shows Train Pipe vacuum level.
4. Vacuum Control Pressure Gauge
It is provided on right control stand. It shows 24 ± 1 psi (1.7kg/cm²) when adjusted by HS-4 valve.
5. Control Air Pressure Gauge
It is provided in Nose compartment or in loco pilot cab, it shows 5.0 kg/cm² when adjusted by NS-1 reducing valve.
6. Fuel Oil Pressure Gauge
It is provided on Nose compartment wall in loco pilot cab, it shows fuel oil pressure in fuel oil system i.e. 4.2 kg/cm².
7. Lube Oil Pressure Gauge
It is provided on Nose compartment wall in loco pilot cab, it shows lube oil pressure in lube oil system i.e. 5.2 kg/cm².
8. Booster Air Pressure Gauge
It is provided on Nose compartment wall in loco pilot cab, it shows ‘V’ gallery air pressure i.e. 1.97 kg/cm².
9. Air Flow Indicator
It is provided on both control stands, connected with air flow measuring valve. It shows rate of air flow between MR2 and brake pipe. It has 0-100 (no. of wagon) marking. It has 2 needles white & red. White shows air flow and red is a reference pointer. When loco coupled with load and BP shows 5.0 kg/cm², that time red needle to be set with white needle. Whenever air flow increase to charge BP, white needle shoot up , do not open the notch till the white needle comes to its original position (on red pointer).
10. Battery Ammeter
It is provided on front panel, it shows charging or discharging rate of battery. It has 0 in center and on either side marking of 200 Amp. On right side it shows charging and on left discharging.
11. Load Meter
It is provided on both control stands, it shows the of current in TM, having each marking of 100 amps.
12. Water Temp. Gauge
It is provided in expresser room engine right side, shows water temperature of cooling water system. It has marking of 0 to 1200
Switches on Loco
1. GFCO – It is provided on both control stands having two positions on & off. When these are in on position and throttle on notches wire no.6 gets energize and GF contactor will pick up.
2. MUSD – It is provided on both control stands having two positions run & stop. It is used to shut down all the loco simultaneously while working multiple units.
3. Head Light Switch – It is a rotating switch and provided on both control stands having six positions Both ‘OFF’ (front & rear),
4. Gauge Light Switch – It is provided on both control stands having two positions ON &OFF.
5. Marker Light Switch – It is provided on both control stands having two positions ON & OFF.
6. Compartment Light Switch – It is provided on both control stands having two positions ON &OFF.
7. Flasher Light Switch – It is provided on flasher light control unit on both control stands. Each box having two switches
8. Battery Knife Switch – It is provided in Nose compartment having two positions CLOSE & OPEN
9. Engine Control Switch (ECS) – It is provided on front panel having two positions IDLE and RUN.
10. Motor Cut Out Switch (MCO) – It is provided on front panel having seven positions and use for isolation of TM.
11. Manual Transition Switch- It is provided on front panel. This switch is used when automatic transition not coming.
Cab Light circuit breaker – It is provided on front panel and protects the cab light circuit.
Engine room light circuit breaker – It is provided on front panel and protects the engine room light circuit.
Dome light circuit breaker – It is provided on front panel and protects the dome light circuit.
Head light circuit breaker – It is provided on front panel and protects the head light circuit.
MB1 – It is provided on front panel, gives battery + ve supply to control circuit and also protects it.
MB2 – It is provided on front panel, gives battery – ve supply to control circuit and also protects it.
MFPB – It is provided on both control stands. FPB – It is provided on front panel and protects the fuel pump motor.
CEB – It is provided on front panel and protects the crank case exhauster motor.
AGFB – It is provided on front panel and protects the auxiliary generator field.
RFCB – It is provided on front panel and protects the radiator fan circuit.
DEB – It is provided on front panel and protects the cyclonic motor.
RBB –It is provided on front panel and protects the rectifier blower motor.
FPB3 – It is provided on front panel/left control stand and protects the fuel pump motor and used to by pass FPC and FPB.
GFOLR (Generator Field over Load Relay) – It is provided on front panel and protects from excess current flow in alternator field.
TDR (Time Delay Relay) –It is provided on front panel, during cranking, if any one of CK1, CK2, CK3 is welded that time this relay will remain energized and protects voltage regulating panel.
BSR (Battery Safety Relay) –It is provided on front panel in WW Governor loco only, it energize when WW governor plunger came out or MUSD on stop position and does not allow the engine to crank hence battery consumption is saved.
CKR 1 & 2 (Cranking Relay) –These are provided on front panel. CKR1 separates exciter shunt field and CKR2 separates auxiliary shunt field during cranking.
ESR 1, 2, 3, 4 (Engine Speed Relay) – These are provided on front panel in EH governor loco and used for increasing and decreasing engine speed. TR (Transition Relay) –It is provided on front panel for parallel transition.
BKR1, 2, 3 (Braking Relay) – These are provided on front panel and it used during dynamic braking. SR (Signaling Relay) – It is provided on front panel and it is used for alarm circuit.
ERR (Engine Run Relay) – It is provided on front panel in WW governor loco only. At the time of power ground, Generator field over load, ECS (Run) ERR de-energize and engine comes to idle.
VAPR (Vent Air Pressure Relay) – It is provided on front panel in alternator loco and protects the rectifier block from insufficient air supply.
Railway Employee (App) | Rail News Center ( App) | Railway Question Bank ( App) | (App) | Information Center ( App) |
This entry was posted in Diesel Loco
New Revised Rates of Railway Quarters w.e.f. 1.7.2023
QUESTION PAPER & ANSWER KEY TECH-III/TRD & TECH-III/ELECTRICAL GDCE 31-05-2022
Result of Train Manager (Goods Guard) Departmental Exam
QUESTION BANK – SELECTION OF JE C & W (Carriage & Wagon) (Hindi & English)
रेलगाड़ी टक्कर बचाव प्रणाली (Train Collision Avoidance System)
During October 2023, RPF reunited over 601 children under Operation ‘Nanhe Faristey’
Regarding Admissibility of training allowance to teaching faculty
रनिंग स्टाफ (Running Staff) सबंधित महत्वपूर्ण प्रश्न के उत्तर एवं स्पष्टीकरण
Promotion Order – Sr. Train Manager (Guard) to Sr. Passenger Train Manage Dt 26.7.2023
Railway Board Order Regarding Duty Hours of Running Staff
Shri Ram Karan Yadav takes over as General Manager, Central Railway
Q Paper & Answer AEN (Assistant Engineer) CBT Exam (Hindi/English) Dt 25.06.2023
Duration of Periodical Medical Examination of Non Gazetted Rly Employee (Rule 514 of IRMM Vol – 1)
जानिए पटरियों के साइड में क्यों लिखे होते हैं नंबर?
KNOW ABOUT – SPL KINDS OF LEAVE – RAILWAY
सहायक लोको पायलट के कर्तव्य (Duties of Assistant Loco Pilot)
Consolidated Orders of MACP Scheme by By Personnel Branch BZA Division
Duties & Responsibilities of Nursing Sister, Staff Nurse & Midwife
NPS – Important initiatives for Central Government employee
प्वाइंटसमेन की ड्यूटी लिस्ट ( list of Pointsman Duty)
GDCE Exam Quota Recruitment Process & Syllabus (ALP & TECHNICIANS POSTS)
Result of Train Manager (Goods Guard) Departmental Exam
गंभीर रोगियों को ट्रेन किराए में 75% तक का डिस्काउंट
Question Paper Ticket Examiner in Level-2 PR Quota 33 1/3% Commercial Department Dated 10.10.2021
QUESTION PAPER & ANSWER KEY TECH-III/TRD & TECH-III/ELECTRICAL GDCE 31-05-2022
Frequently asked Question (FAQ) On Privilege ePass / PTO
Question Paper With Answer of Chief Loco Inspector in Level 7 (ER) dt 08-09-2019
Question Paper & Answer – Goods Guard Selection Exam dt. 28.08.2022
Q PAPER – SELECTION OF STAFF & WELFARE INSPECTOR – SWR – 2011
राजभाषा पर विभागीय परीक्षा के लिए उपयोगी प्रश्नोतर
APPLICATION FORM FOR (I) INTER RAILWAY (II) INTER DIVISIONAL/ DEPARTMENTAL TRANSFER (III) DEPUTATION
APPLICATION FORM FOR (I) INTER RAILWAY (II) INTER DIVISIONAL/ DEPARTMENTAL TRANSFER (III) DEPUTATION
गंभीर रोगियों को ट्रेन किराए में 75% तक का डिस्काउंट
गुड/वैरी-गुड के चक्कर में फसेंगे कर्मी…. Chamchagiri Bahot Jaruri Hai
Post Retirement Complementary Passes For Railway Employees – Revised Entitlement
Clarification on Promotion Effecting Reservation (RBE 91/2018 dated 19.06.18)
Result of Train Manager (Goods Guard) Departmental Exam
Refund Rules of Unreserved & Reserved Tickets of Indian Railway
Good News – Modification of Recruitment Rule of Train Manager (Guard)
रेलवे के साफ्टवेयर में सेंध कर फर्जीवाड़ा
Vacancy Notification – Filling up of Various Ex-cadre posts of IRIEEN, Nashik road
Regarding Minimum Service Conditions For GDCE (General Departmental Competitive Examination )
Syllabus – Section Controller (Traffic)
Materials Management on Indian Railways (English)
Trouble Shooting -SUB SYSTEM – 19 TRAIN BUS- ACT (RS) – ABB Loco (English) (Part – B)
रेलवे में पति-पत्नी एक जगह होंगे तैनात
Are you sure you want to delete this element?
Close